The Quality Assurance program plan contained herein is divided into 19 sections and related attachments, which describe and establish the assurance and control system used by the company in the design or interpretation of design and design change control, construction; Inspection, service supply and Earthling and general
engineering activities.
This plan shall include a description of the procedures, instruction, and measures used to assure that design documents; inspection, materials and workmanship are controlled in accordance with specified contract requirements. The plan is directed towards implementing and enforcing the quality assurance and quality control
requirements for safety related structures, systems and components, and for providing compliance with specified requirements. In this regard, a listing of the items to be covered by the requirement(s) of this plan and related procedures. Instructions and drawing shall be issued by NOGAD GLOBAL SERVICES LTD.
Project procedural controls shall be developed and administered by NOGAD GLOBAL SERVICES LTD project management team. A separate and independent quality assurance surveillance and audit activity shall be provided by the NOGAD GLOBAL SERVICES LTD Quality Assurance Representative to cover those project
functions\activities performed. CONTROL AND ISSUANCE OF PLAN This plan shall be prepared, approved, maintained and distributed by the NOGAD GLOBAL SERVICES LTD Quality Assurance Representative – (referred to as the issuing Authority). In addition, prior to initial release of the plan, approvals shall be obtained from NOGAD GLOBAL SERVICES LTD project manager and quality assurance manager.

Approval signature of these individuals shall be shown on the “second page” of this document. Revision of this plan shall be handled in the same manner as prescribed for initial release. Copies of the plan shall be issued by NOGAD GLOBAL SERVICES LTD quality assurance representative.

 

CONTROLLED COPY
Distribution of controlled copies shall be made to personnel who require continued use of the plan. The need for  issuing controlled copies shall be determined by the issuing Authority. Controlled copies shall be numerically controlled and updated as revisions or additions to the plan. An authorized distribution list for such copies shall
be maintained by the Issuing Authority in accordance with the project document distribution plan.

 

UNCONTROLLED COPY
Distribution of uncontrolled copies shall be made to personnel who need access to the plan for information purposes or limited reference use. NOGAD GLOBAL SERVICES LTD or the issuing authority shall not be held responsible
or accountable for the status, use or withdrawal of such copies from circulation.
REVISIONS
Revisions to the plan shall be identified by a revision number (e.g. Rev 1) which shall be annotated in the cover page and in the space provided at the top of each page. When a revision is distributed, a covering letter shall be issued by the issuing Authority explaining the revision(s) made, and instructions for filling. PROJECT MANAGER
The project manager is generally responsible for the satisfactorily execution of projects, services, supplies, and inspection of the assigned work in conformity with the approved design documents and the contractual requirements in terms of quality, safety, efficiency and schedule. He is responsible for:
(a) The proper implementation and satisfactory operation of the Quality Control Procedure
(b) Assuring that all construction operations and materials are in compliance with contractual requirements, the Quality Assurance program plan and the approved project quality control system which comprises of Administrative
procedures, Quality Control procedures and work instruction(s).
(c) Approving the Quality Assurance Program and requesting services necessary to
assure implementation of this program procedures and instructions and other
project requirements.
Request full document